Hello, TheNextOne!
I
think I know what the problem says . . .
\(\displaystyle \;\;\)but I still don't have a reasonable set-up.
Magna Inc. sells and manufactures two products- Product A and Product B.
The cost to produce Product A and Product B are $36 and $45 respectively.
8,000 units of Product A are needed and 11,000 units of product B are needed.
These products are produced by a machine.
2.5 machine hours are needed to produce one unit of A, and 3 hours for each B.
In total, there are 41,000 machine hours that need to be used up.
Netscape company offers to manufacture and sell the products to Magna
for $33.75 per A and $40.50 per B.
How much of each product should Magna purchase and produce
in order to minimize costs given that the 41,000 machine hours must be used up?
If Magna tries to produce all the products itself, there are not enough machine hours.
8,000 A's at 2.5 hours each = 20,000 hours.
11,000 B's at 3 hours each = 33,000 hours.
\(\displaystyle \;\;\)The total (53,000) exceeds the maximum of 41,000 hours.
So, we assume that Magna will produce
some of the A's and buy the rest from Netscape.
Similarly, Magna will produce
some of the B's and buy the rest from Netscape.
Let \(\displaystyle x\) = number of A's that Magna will manufacture.
Then it will buy the other \(\displaystyle 8,000 - x\) units from Netscape.
Let \(\displaystyle y\) = number of B's that Magna will manufacture.
Then it will buy the other \(\displaystyle 11,000 - y\) units from Netscape.
The cost of making \(\displaystyle x\) units of A is: \(\displaystyle 36x\) dollars.
The cost of buying \(\displaystyle 8000-x\) units of A from Netscape is: \(\displaystyle 33.75(8,000-x)\) dollars.
\(\displaystyle \;\;\)The total cost of getting 8,000 A's is: \(\displaystyle \,36x\,+\,33.75(8,000-x)\) dollars.
The cost of making \(\displaystyle y\) units of B is: \(\displaystyle 45y\) dollars.
The cost of buying \(\displaystyle 11,000-y\) units of B from Netscape is: \(\displaystyle 40.50(11,000-y)\) dollars.
\(\displaystyle \;\;\)The total cost of getting 11,000 B's is: \(\displaystyle \,45y\,+\,40.40(11,000-y)\) dollars.
Hence, the total cost is: \(\displaystyle \,C\:=\:[36x\,+\,33.75(8,000-x)]\,+\,[45y\,+\,40.5(11,000-y)]\)
And we must minimize: \(\displaystyle \,C\;=\;715,500\,+\,2.25x\,+\,4.5y\)
The only constraint (other than \(\displaystyle x\,\geq\,0\) and \(\displaystyle y\,\geq\,0)\,\) is the number of machine hours available:
\(\displaystyle \;\;\;2.5x\,+\,3y\:\leq \:41,000\)
Is that it?