The boss of your company invites you into his office. He tells you that he needs a certain task completed. You know that the last time he asked you for this task to be completed, it took 16 people 4 days to finish. If he says he needs the task to be completed in 3 days, how many people are you going to need? (Round up to the nearest person.)
If instead he says that you can only use 10 employees (which includes yourself), how long will it take to complete the task? (Round to the nearest hour.)